There's been exciting progress at our M6 J19 improvement scheme over the past few weeks, with 36 steel beams now safely in position over the carriageway.
MPB is completing all of the reinforced concrete on the project, including the bridge deck. Between August and December 2020 we placed nearly 5000 cubic metres of concrete.
The project, working with Amey and Sir Robert McAlpine for Highways England, centres on the addition of a two-way link across the junction to allow better connection between the M6 and A556, including a new bridge spanning the M6 motorway within the roundabout.
A video showing recent progress can be viewed here.